Construction on the trailer is on schedule.
The first five weeks of construction are consumed by the infrastructure
assembly of the interior and exterior of the trailer to include running
all the electrical, plumbing and bracing. Over the next 9 to 10 weeks
project will accomplish the following:
- Complete the framing requirements for the windows, doors and interior
- Install the finished flooring and painting the interior of the unit
- Mounting all the casework and countertops
- Installing the entrance and the ceiling
- Complete installation undercarriage to include the water system,
generator and hydraulics
- Installations of the eye testing equipment
- Graphics application
- Testing all the electrical and plumbing systems
- And finally, a thorough inspection and road test.
|
|
|